My Lords, this group deals with Parts 9 and 10 of the Bill. Providing suppliers with an effective remedy is not only required by the World Trade Organization’s Agreement on Government Procurement, the GPA—a very important international agreement—but a critical aspect to any well-functioning and accountable procurement regime. It gives the market

confidence to invest resources participating in government procurement, knowing that public contracts will be awarded fairly and transparently.

As such, in most cases, suppliers have 30 days from the point at which a breach should have been discovered to raise a claim, and in the majority of procurements a standstill period will apply. The standstill period of eight working days is a short pause between the point when the contract award decision is notified to bidders and the final contract conclusion. It allows bidders to consider the assessment summary, which includes evaluation feedback.

If a claim is filed at court during the standstill period, an automatic suspension will apply, preventing signature of the contract until the legal claim is resolved or the suspension is lifted on application of the contracting authority. If the standstill passes without challenge, it protects against the contract being set aside after it goes live. Clearly, we do not want court proceedings to be the only way to motivate contracting authorities’ compliance with the new Act, which is why we have introduced the procurement oversight regime in Part 10, which will enable an appropriate authority to investigate non-compliance, make recommendations and issue guidance across all contracting authorities, as a result of the investigations. This will encourage the consistency and continuous improvement we all want to see.

Government Amendments 263 and 266 correct the reference to the contract award notice in Clause 49(1)(b) and (4) respectively.

Amendments 265, 267, 393 and 394 make it clear that any time a contracting authority chooses to enter into a standstill period, which is known as a voluntary standstill period in circumstances where the Bill does not mandate a standstill period, it must match the mandatory standstill period and be for a minimum of eight working days.

Amendment 461 clarifies that failure to have regard to the national or Welsh procurement policy statements is not enforceable via Part 9.

Amendments 464 to 469 make some textual amendments and make it clear that the automatic suspension applies only when a claim has been notified during the standstill period.

The structure and drafting of Clause 95 will be amended by Amendments 470 to 476 to make the intent of the clause easier to interpret.

There are various amendments related to oversight functions. Amendment 481 to Clause 96 makes a straightforward clarification to the meaning of “section 97 recommendation”. Amendments 483 and 484 reflect the principle that an appropriate authority may issue guidance to contracting authorities only in line with restrictions on relevant authorities in Clauses 99 to 101. Amendments 501 and 502 amend Clause 101 to reflect agreements with devolved authorities that, where appropriate, UK government Ministers can issue guidance under Clause 98 to all contracting authorities, including devolved and transferred authorities, to maximise joint working and efficiency.

I pause at this point so that my noble friend Lady Noakes and others can speak to their amendments.