Nuclear Energy (Financing) Bill

It will be no surprise to hear that I have no confidence that the true costs of nuclear waste disposal are actually included. We hear that this is rolled up in the strike rate for Hinkley, but if something happens and EDF goes out of operation, who will pick up the additional costs? It will clearly be the bill payers or the taxpayer. We hear about the fact that nuclear is supposed to be clean energy, but how can it be classed as clean energy when we are burying radioactive waste and having to store it for up to 1,000 years? That, to me, does not mean clean energy.

Taishan in China was held up as an exemplar EPR project when it was commissioned, but it has been offline since June this year due to safety concerns and rod damage. It is clear that the design and construction of EPR nuclear stations has still not been bottomed out properly. As the shadow Minister, the hon. Member for Southampton, Test (Dr Whitehead), said, a reliance on French state-owned EDF and the Chinese state company China General Nuclear kind of undermines the argument about having sovereign energy security. It makes no sense.

Despite the cost and programme issues at Hinkley, we are told that Sizewell C will somehow be different. There will be cost savings from learning on Hinkley. The design will be replicated, saving more money, but the reality is that the site at Sizewell C is bound to have different ground conditions, different environmental considerations and different logistics and site constraints, which affects methods of working, and that means that we cannot build an exact duplicate station the same way.

Even if savings are realised on Sizewell C compared with Hinkley, what does that mean cost-wise? If Sizewell C saves 25% compared with Hinkley, that is still a capital cost outlay of £18 billion. Surely there are better ways to spend £18 billion. We heard from the right hon. Member for Kingswood (Chris Skidmore) about the number of jobs being created. If I was given £18 billion to £20 billion, I am sure that I could create 30,000 jobs —by the way, that is £730,000-odd a job in capital costs alone. That is not a good return.

On costs, we are told that a new deal signed under the proposed new funding model in the Bill will cost consumers only £1 a month during construction, but if we look at a 10-year construction period for Sizewell C, we see that that means that bill payers in 28 million households will pay £3.4 billion before it is operational. That is a further £3.4 billion in expenditure when that money could be better invested elsewhere.

We still do not know with this Bill what the long-term pay-back options will be. Will there be a further agreement on the strike rate or a minimum floor price on the sale of energy? What length of contract will bill payers be tied into once a RAB model for an agreement is signed off?

What else could we do with that amount of money? We could upgrade all homes to energy performance certificate band C. We could have wave and tidal generation. The UK Government are willing to introduce the Bill and commit hundreds of millions of pounds to nuclear—the Budget has £1.7 billion just for developing nuclear to a negotiation stage—but they will not even ringfence £24 million for wave and tidal in pot 2 of the forthcoming contracts for difference auction. The disparity is clear.

It is time the Government took their blinkers off. It will be a real disgrace if they do not provide a pathway for wave and tidal projects to scale up. Scotland is currently leading the world on the issue; the O2 tidal generator is operational and grid-connected in Orkney. I hope that the Minister will reconsider the request to ringfence a small amount of money in pot 2 of the forthcoming contracts for difference auction.