Not for the first time I think I am going to express a minority view in the Chamber, but I am sure everyone will listen carefully and, once I present my arguments, change their minds and agree with our point of view.
The real debate is whether we need new nuclear or not. I intend to spell out why we do not need new nuclear and, therefore, why we do not need the Bill. Before doing so, I want to highlight the UK Government market failures that have led to the Government scrambling to bring forward the Bill.
We know that Hinkley Point C is currently under construction, but it is under construction as the most expensive power station in the world. There are several reasons for that and how it came about. First, successive Governments seem to have developed a groupthink, following lobbying from the nuclear industry, that somehow nuclear is a prerequisite for our future. Then came the rationale that building a suite of new large-scale nuclear power stations would lead to competition and cheaper costs. However, that philosophy was flawed in that there were not enough competitors to start with and then a piecemeal approach was taken by nominally awarding sites to different preferred bidders. For Hinkley Point C, that meant EDF was the only game in town, so there was no competition when negotiating the contract. EDF had already been beset with problems with its EPR prototypes in Finland and France, so it had to be more cautious in its pricing. It is little wonder then that the UK Government ended up with such a bad deal. They have since tried to tell us that the eye-watering strike rate of £92.20 per megawatt hour for a 35-year contract, while the cost of offshore wind dropped to £40 per megawatt hour for just a 15-year concession, meant that the nuclear deal was a good deal.
In a letter last week, the Minister of State, Department for Business, Energy and Industrial Strategy, the right hon. Member for Chelsea and Fulham (Greg Hands), was effectively saying, “By the way, the Hinkley Point C deal was actually rubbish and poor value for taxpayers, so now we have an alternative funding model and we’re bringing that forward.” Interestingly, it was stated in the letter that the new funding model could potentially save the taxpayer £30 billion to £80 billion. How much money do the Government estimate has been wasted on Hinkley? How many billions of pounds are the Government willing to commit bill payers to if they say they can save up to £80 billion? Logic says that hundreds of billions of pounds would have to be spent to be able to argue that there could be a saving of £80 billion. I will happily give way to the Under-Secretary of State for Business, Energy and Industrial Strategy, the hon. Member for
Mid Norfolk (George Freeman), if he can tell me how much money that £80 billion saving is estimated on? The right hon. Member for Chelsea and Fulham would not give way, but I am happy to give way if the hon. Gentleman can tell me how much the Government estimate—[Interruption.] I take it that he will not give us a figure. The Minister will not come forward and give a figure. That does not add confidence. The Government are saying the saving could be between £30 billion and £80 billion. That is a huge range and that does not give confidence to the estimating proposals either.