Procurement Bill [HL]

My Lords, this next group refers to utilities. Amendments 11, 13, 14, 17, 20, 21, 22, 169, 174, 180 and 184 relate to an exemption for utility activities exposed to competition. The amendments to Clause 5 and Schedule 4, and a consequential amendment to Schedule 2, are again in response to the concern of the DPRRC that the power to establish a procedure to exempt utilities subject to competition from the Bill amounted to a skeleton clause. The Government will replace this power with one that requires the exemptions to be made by secondary legislation under an affirmative procedure. This will afford Parliament greater scrutiny to review each exemption. The test to be satisfied for an exemption remains that there is fair and effective competition in the relevant utility market, and that entry to that market is unrestricted.

Noble Lords should note that Amendment 22 adds Part 2 to Schedule 4, which sets out the utility activities which are exempt from procurement regulations. These reflect exemptions that exist under the current regime, which are preserved by Amendment 169 in order that they are available under the Scottish procurement regulations.

Amendments 174, 180 and 184 ensure that the affirmative procedure applies to an exercise of the power.

Amendments 15 and 16 ensure that the definition of private utilities and contracting authority interact as intended and that a private utility is only a contracting authority in respect of the utility activities for which the utility has a special or exclusive right.

Amendments 18 and 19 revise the description of a utility activity in the transport sector in paragraph 4 of Schedule 4.

Amendments 56, 71 and 200 speed up procurements and reduce the burden for utilities using a utilities dynamic market—a UDM—by only requiring utilities to provide tender notices of upcoming procurements to suppliers on a UDM or appropriate part of a UDM, instead of having to publish notices. In practice, this means utilities can, for example, provide the tender notice to suppliers on the UDM as part of the associated tender documents as each procurement under the UDM is commenced.

In order to take advantage of this flexibility, the notice setting up the UDM must meet minimum information requirements, which will be set out in regulations under Clause 88. Utilities must specify in the UDM notice that only members of the UDM will be provided with tender notices. The notice setting up the UDM will be published continuously and will remain open so new members can join at any time. If accepted, they would then be entitled to receive tender notices.

Amendment 77 to Clause 48 will allow private utilities to adopt a voluntary standstill period to direct award contracts instead of a mandatory one. This means private utilities will take a risk-based decision on whether to apply a standstill period to a direct award procurement. It is in keeping with only regulating private utilities’ procurement to the extent necessary under our international obligations. I will turn to the amendment in the name of my noble friend Lord Lansley in my closing speech, having heard the points he raises. I beg to move.