Infrastructure Planning (Electricity Storage Facilities) Order 2020

I thank your Lordships for their valuable contributions to this debate. I conclude by emphasising the importance of the changes contained in this SI. The Government are committed to removing barriers to the deployment of electricity storage. The Government and Ofgem’s 2017 smart systems and flexibility plan sets out a range of actions that will be taken to enable the transition to a smarter and more flexible energy system.

This SI will remove electricity storage, except pumped hydro, from the national planning regime in England and Wales. It will result in an appropriate planning treatment for electricity storage. Sizing and investment decisions will be based on a project’s economic potential or capability to store renewables, rather than whether it falls under the NSIP threshold. We estimate that this legislation could save the industry between £0.5 million and £7 million annually.

The noble Lord, Lord Berkeley, asked about pump storage in England—actually, in all places—offshore. To clarify, we are applying this onshore and offshore for legal consistency. We are not aware of any developments of offshore storage. However, storage located offshore, should it be developed, would need to seek planning permission. In Wales, it would need a marine licence from either the Marine Management Organisation or Natural Resources Wales, so there is an element of future-proofing this legislation.

The noble Lord, Lord Berkeley, and the noble Baroness, Lady Bennett, asked whether, given the enormous demand for storage in the future, this will be sufficient

in meeting the demand for storage. We are taking a number of steps to remove barriers, reform markets and invest in innovation through the 2017 smart systems plan, including ending double payment of network and policy costs and making it easier to connect to the grid. We have made good progress in improving the regulatory and investment landscape for storage, and we are working closely with industry to develop the next phase of work under the smart systems plan.

The noble Baroness, Lady Bennett of Manor Castle, also asked about promoting household batteries. I wholeheartedly endorse her enthusiasm for these—and indeed for solar panel roof tiles. We have made good progress in improving the regulatory and investment landscape for storage, and we are working closely with industry to develop the next phase of work under the smart systems plan, including addressing barriers to domestic storage. The noble Baroness also made the point that saving energy is at least as important as generating it, which we should all keep in mind.

My noble friend Lord Robathan asked about the progress of battery storage development. There is currently about one gigawatt of battery storage in the GB system; the majority of this has been deployed since 2015. There are about nine gigawatts of storage in the planning pipeline, six gigawatts of which is battery storage and three gigawatts of which is pumped hydro.

My noble friend also asked about investment in new types of battery technology. We have launched a range of innovation competitions as part of our £70 million innovation funding for smart systems. This included a £20 million competition for demonstrating innovative storage technologies. As well as this, we have allocated £317 million to the Faraday battery challenge.

The right reverend Prelate the Bishop of Salisbury asked what additional funding will be given to local authorities. They already have experience of dealing with storage projects below 50 megawatts. We expect, with this legislation, to encourage projects to deploy at a larger scale rather than bring forward new projects. We are working with MHCLG to update the planning practice guidance to refer to storage. I will write to the right reverend Prelate on the possibility of future opportunities to discuss the Environment Bill. He also asked about support for rooftop solar generation; I will write to him with further detail on the actions that we are taking to support this.

In response to my noble friend Lady McIntosh of Pickering’s question about making electricity storage flood-proof, although her point is also applicable to other energy infrastructure, the planning system requires developers and decision-makers to consider the impacts of flooding on the projects in question. This will require consultation with the Environment Agency and other relevant bodies to ensure that any risks to infrastructure are thoroughly considered at every stage of the decision-making process. Following Sir Michael Pitt’s recommendations, guidance for local authorities in relation to this matter is now set out in the National Planning Policy Framework.

My noble friend also asked that local communities be involved in these decisions. These changes mean that storage facilities will generally be consented by the local planning authority, involving local communities in such decisions.

The noble Lord, Lord Grantchester, asked about the threshold for pumped hydro storage. There is no evidence to suggest a higher threshold is needed here. The analysis shows that the planned impacts of pumped hydro will be in an order of magnitude higher than other storage technologies, meaning that the NSIP regime is the most appropriate planning route. A 50-megawatt threshold is consistent with hydro generation, which has similar planning impacts.

The noble Lord also asked about our commitment to define storage in primary legislation. This is an important commitment, and one that we will honour when parliamentary time allows.

Several noble Lords asked about the development of pylons. I am afraid that I cannot give a detailed answer now; I will write to them on this.

To achieve net zero at the lowest cost, we will need significant levels of flexibility to integrate high volumes of low-carbon power, heat and transport. This will require a significant increase in the deployment of electricity storage. The changes contained in this order help to unlock the potential for large-scale storage facilities critical for meeting net zero.

To close, I will once more emphasise the importance of this order in removing a key barrier to the deployment of large-scale storage facilities. Approval of this order will help to bring forward such facilities, supporting low-carbon jobs and enabling us to maximise the output of our renewable generation and progress towards meeting net zero.