My Lords, I will briefly ask the noble Baroness a couple of questions on this Motion. It is good to have it before the House—it shows progress with HS2—but I am wondering why today. It is probably because we do not have much else to do in your Lordships’ House. Could she give us any idea as to when the Bill will complete its passage through the House of Commons and when we might see it?

Before the Bill comes to your Lordships’ House, will the Government publish a new business case and cost estimate for phase 2a—the subject of the Bill—taking into account the latest information about land purchase and design development? I am already hearing stories about quite difficult ground conditions on the route, including salt mines. There are lots of salt mines in

Cheshire. Let us hope that the costs estimate does not go shooting up. I ask this because on HS2 phase 1 we are still working on the 2013 business case, which is six years old—six years of the Infrastructure and Projects Authority’s amber/red designation, which I think is a record.

This was raised in the House of Lords Economic Affairs Committee hearing last week, when Nusrat Ghani, the Minister, and officials gave evidence. When they quoted higher costs to the Minister—I think she had probably gone to vote by then—the officials said, “We don’t recognise these figures”. When the committee went back to them and said, “If you don’t recognise the figures we’re quoting, what figures do you recognise?” The answer was, basically, “None”. I do not know whether this is the first of many Treasury blank cheques, or whether in fact the Minister will confirm, as she did in a Written Answer to me about six months ago, that before permanent work starts on phase 1, the Government will come up with a new cost estimate and a new business case.

Type
Proceeding contribution
Reference
795 cc996-7 
Session
2017-19
Chamber / Committee
House of Lords chamber
Back to top