Energy Bill [HL]

Proceeding contribution from Lord Wallace of Tankerness (Liberal Democrat) in the House of Lords on Wednesday, 21 October 2015. It occurred during Debate on bills on Energy Bill [HL].

My Lords, I think that everyone who has dealt with this Bill would agree that it has not been a satisfactory process. We have had late tabling of amendments; even the amendments before us were tabled only on Monday, meaning that if we wished to table amendments to amendments we were under considerable pressure to do so.

Perhaps I may put in context what we are discussing by drawing to the House’s attention what was said yesterday in the Select Committee on Energy and Climate Change in the other place. My right honourable friend the Member of Parliament for Orkney and Shetland asked the noble Lord’s ministerial colleague, Andrea Leadsom, “So what is the purpose of the grace period, then?” To which she replied, “As I say, to ensure fairness—to ensure that those who have spent money in a significant investment and achieved everything technically to meet the cut-off date, but through reasons beyond their control have not actually made it, are not penalised for reasons beyond their control”. It is with these words in mind that we must examine the Government’s position and the amendments that have been put forward. As the noble Baroness, Lady Worthington, said, an estimated £350 million has been put in to take forward projects which may not now proceed.

Our amendments relate in one respect to all applications which were in train at the time of the somewhat arbitrary date of 18 June—that was the date that Secretary of State made a Statement; it has no more magic than that—and which had received planning committee approval. The reason for emphasising committee approval was that, in an earlier clause in the Bill, the Government set great store by the fact of local determination. A local determination means that, after considerable discussion, debate and consultation, the local planning committee has approved a particular proposal. It may just be that it is due to the cycle of planning meetings that the application has not yet gone to the full council for endorsement. I refer back to what the Minister, Ms Leadsom, said about applicants achieving everything technically to meet the cut-off date, but through reasons beyond their control, have not actually made it. A lot of developers do not have control over the cycle of meetings of a local authority and it seems very unfair that, if they have passed muster after scrutiny by a planning committee, they fall foul because the full council has not ratified that decision.

Our Amendment 78RA contains a provision that it should refer to planning applications that were in place and had been accepted 16 or more weeks before 18 June. The reason for that is that after 16 weeks it is possible, if the local authority has not made a determination, for the developer to say that there has been a non-determination, so it is a deemed refusal and to appeal to Ministers on that basis. But the noble Lord and others who were at the Committee debate last week will remember that I gave an example from, I think, Tayside where extensive work had been done in terms of discussions between the developers, local communities and the planning authority to try to

ensure that concerns had been meet and the opportunities to work with other environmental projects going on in the area were maximised. I believe, along with I am sure most Members of your Lordships’ House, that it is good practice for developers to work alongside the planning authority and try to get an agreement and outcome that is satisfactory to all. And yet, if the developer did that and missed the 18 June cut-off date, it will be penalised for it, whereas those about whom it might be said that they are not using best practice—I would not necessarily say that it was bad practice—might take a slightly legalistic view and say, “Well, it has been 16 weeks, so that is it. We are going to appeal because there has been a deemed refusal”. If that is subsequently granted on appeal, their applications will be satisfied. That does not appear to be a fair way of proceeding. If we are looking for an element of fairness in this, where is the fairness in penalising those who have demonstrated good practice?

Also with regard to Section 75 and Section 106, the Minister said in his letter to me that, where the planning committee could have been minded to approve on or before 18 June subject to Section 75 or Section 106 agreements but no formal consent was granted on or before 18 June, unfortunately, there is no legal consent given that they are minded to approve and we understand that the negotiations can be lengthy and not always successful. People from the industry who have been talking to me find that an unduly legalistic approach. The industry has been working with planning authorities for some 10 years on the Section 75 or Section 106 agreements that emerge in these situations. By and large they are already negotiated, but it may take time to put in place some of the detailed provisions. For example, if it is part of the development that there has to be a new habitat on neighbouring land—not the land on which the development is to take place—it has to be shown that the developer has the right to undertake the building of the habitat on that land. That is part and parcel of what happens and it is both practical and common sense that it should be recognised. Again, reminding us of what the Minister’s colleague said, it is to ensure fairness so that people are not penalised for reasons that are beyond their control.

Perhaps I may also take up what the Minister said on the question of variations. He helpfully stated in his letter to me and then repeated it in the House just a moment ago that, where consent is granted for a development on or before 18 June and is subsequently varied in this way, it will continue to fall within the approved building condition in proposed new Section 32LJ. I raise this because it is helpful that the Minister has now put this on the record, but I have also had representations from those who have taken legal advice that they do not necessarily believe that it does what the Minister says. I would ask him to look at it again. The fact that we have something that could be referred to in a Pepper v Hart way is helpful, but some would find greater reassurance, and it would be clearer to me, if there is something on the face of the Bill.

I refer to Amendments 78RA and 78RB with regard to Section 36 of the Electricity Act 1989. The purpose and effect of these amendments is to address what we believe is an anomaly by applying the principle of

proposed new Section 32LJ(4)(b) to an analogous position under the Section 36 regime. Under Section 36 of the 1989 Act, the relevant planning authority is not the decision taker, but it can object to the proposal, after which there must be a public inquiry and then a decision by the Secretary of State. That is closely analogous to refusal under local planning followed by an appeal, and indeed for around half of the affected projects DECC’s renewable energy planning database describes the projects as being at appeal. Indeed, the last time that the people briefing me looked at the DECC website they were described as being at appeal. However, the proposed provisions cover the local planning version of this process but not the Section 36 version. This means that small extensions of larger sites, which have to follow the Section 36 route, are going to be treated less favourably under these grace period provisions than some sub-50 megawatt, stand-alone developments which go ahead under the local planning process. Reverting back to the question of fairness, there should be consistency in the Government’s approach. This amendment seeks to ensure that, and I hope the Minister will think again on it.

I also draw the Minister’s attention to the fact that, because of the Planning Act 2008, which has superseded Section 36 in England and Wales, that section mainly affects plants in Scotland. The functions of the Secretary of State under Section 36 and Schedule 8 are transferred to Scottish Ministers under Article 2 of the Scotland Act 1998 (Transfer of Functions to the Scottish Ministers etc.) Order 1999, so far as they are exercisable in or as regards Scotland. Accordingly, the amendment does not explicitly refer to devolved Ministers. Would the Minister look and see if it is the case that they are not covered? I am sure he would not wish to put Scottish developers in any less favourable position than those in England and Wales.

We have proposed a relatively simple amendment regarding grid works, with a different cut-off date for grid works agreements. In Committee and subsequently, I raised with the Minister a case involving a joint venture between an energy company and a private individual. The energy company carried on the transmission entry capacity for a substation but the joint venture finished and the private individual carried on himself. Transmission entry capacity has therefore been lost and has to be reapplied for. It has had that connection for five years in the past but, crucially, did not have it on 18 June. It seems very unfair that they should lose out in a very bureaucratic process. We tried to find a way to capture that in an amendment and we thought we would do this by putting in a different end date, because you cannot just conjure up a grid connection agreement. It would not have taken any more capacity than was already the case, but this might give some clarity.

In another circumstance which has been drawn to my attention, changes were made. Grid capacity that was for one developer was then to be shared and this required a new agreement to be made. There was a clerical error and the developer sent the agreement back to get this sorted. Unfortunately, it was sent just before 18 June and did not come back until after that date. It would be reassuring to know whether that counts as a variation or whether it could be addressed by extending the period for grid connection.

In the recommittal, I made a point about radar and the problem developers are finding with the length of time it is taking the Ministry of Defence to process applications. The grace period that has been given may, therefore, not be effective because of the time it takes to get agreements reached. One developer who has made representations has said, about a particular mitigation which the MoD is looking for: “There are no guarantees that the work programme will deliver mitigation at this stage. In any event, the current MoD position is that the first part of the variation condition allowing development to commence cannot be discharged before 2018. There are some ongoing discussions between onshore developers and the MoD, seeking to find ways of earlier condition discharge but this is proving problematic. Overall, the costs and timescales of this ATC radar mitigation programme do not fit with any of the onshore projects”. It would be perverse if delay on the part of the Ministry of Defence meant that the grace period which the Government have sought to give does not actually cover these circumstances. This is why we have put in a particular date, though it may be that March 2018 is too early. I hope the Minister will take that serious point about trying to get agreements out of the Ministry of Defence if he wishes to give substance to what he sought to do with the radar works part of his amendment.

I am sorry to take up time but I had a lot of important points. I hope that the Government will move. I do not believe that they have met the letter or the spirit of what Andrea Leadsom said yesterday to the Select Committee in the other place.

4.15 pm

Type
Proceeding contribution
Reference
765 cc674-7 