Energy Bill [HL]

Proceeding contribution from Lord Hardie (Crossbench) in the House of Lords on Wednesday, 21 October 2015. It occurred during Debate on bills on Energy Bill [HL].

I would like to ask the Minister about the extension of time. I fully understand and think it is fair that there has been an extension of time where planning permission is granted on appeal. However, did I understand the Minister to say that, where permission was refused on appeal, and if there were a judicial review that ultimately granted permission, that would be respected and it would be deemed to have been an appropriate permission? What concerns me is the timescale, if my understanding is correct. How many years down the line are we talking about

beyond June 2015? Once we go down that line, for perhaps two years, that might have an impact on meeting the 2019 deadline.