Growth and Infrastructure Bill

I thank those noble Lords who have taken part in this rather interesting and short debate. I will try to pick up some of the matters raised, either as we go through or subsequently. Perhaps it would be helpful if I explain the Government’s rationale for Clause 24 and the reforms within it. As we have said on many occasions, one of the Government’s top priorities is to get the economy growing by creating the right conditions for growth. This includes ensuring that the planning system is operating in the most efficient and effective way. Clause 24 will support this aim by allowing developers of nationally significant business and commercial development to request to use the streamlined planning regime set out in the Planning Act 2008.

The noble Baroness’s Amendments 77A, 77B and 78A would remove the ability of the Secretary of State to issue a direction for prescribed forms of business and commercial development in response to a request from a developer. I have listened to views expressed that business and commercial planning applications should be determined by the local planning authority, and we have no difficulty with that. The Government agree that that is the right approach in the vast majority of cases. However, there will also be a small number of projects that will be of national economic importance

and, in certain circumstances, it will be right that a decision on such proposals is taken at the national level by democratically elected Ministers.

We are not proposing that that should be a mandatory route for developers; it is optional. Developers of major projects will choose to request to use the infrastructure planning regime only if it offers other benefits which the local authority cannot provide, such as statutory timetabling—the noble Baroness asked me what it would be—and the one-stop shop, which will be useful where multiple consents are required.

Any request made to use the infrastructure planning regime will also be subject to the agreement of the Secretary of State, who will have to be satisfied that the proposed project is of national significance. Under Section 35(10) of the Planning Act, the Secretary of State is required to give reasons for his decision when making a direction, and that requirement is carried forward in new Section 35ZA(10) in Clause 24. That is why we cannot accept Amendment 77ZK, which is unnecessary.

My noble friend Lord Jenkin spoke to Amendment 78B, which would limit who can make a request that an application or proposed application for energy, transport, waste, water or waste water projects below the Planning Act thresholds should be directed into the nationally significant infrastructure planning regime. I understand why the amendment has been tabled and am sympathetic to its aims, but perhaps I may explain why we have set out a different approach in the Bill for business and commercial schemes.

The Planning Act sets specific thresholds for energy, transport, water, waste and waste water projects. Any proposal for a development which meets those thresholds must seek planning consent through the nationally significant infrastructure planning regime. Section 35 of the Planning Act allows a request to be made to use the regime for projects which are below the thresholds. We have not sought to limit who can make a Section 35 request for infrastructure projects as we recognise that other parties may hold information which could indicate that the project was one of national significance and should be directed into the regime. However, for business and commercial schemes, the Government have been very clear that for developers of major schemes this is an optional route. Therefore, the limitation on who can make a request is not there. We believe that it should be for a developer or applicant to determine whether the advantages of using the infrastructure planning regime outweigh the usual route of making a planning application to the local planning authority. The Secretary of State will direct a project into the regime only if he considers that it is of national significance.

Concerns have been expressed that if we do not accept the amendment the Secretary of State will be inundated with requests from third parties, or that there will be delay to the application being submitted or to the local authority decision-making process. We think that this is unlikely. We are aware of only a very small number of such requests having been made to date. The impact assessment states that the figure is likely to be between 10 and 20 a year. We will have to see how that works out.

If an application or proposed application is directed into the nationally significant infrastructure regime, this does not mean that local opinions will be ignored. Developers will have to consult local communities, and local authorities will continue to play an important role. The consultation requirements of the Planning Act, as noble Lords will know, are rigorous. Local authorities will also be invited to prepare a local impact report. The Secretary of State must have regard to the report as well as to other matters that are both important and relevant in making his decision on the development consent order application. The local plan, for example, is likely to be both important and relevant, as indeed is the National Planning Policy Framework.

It is essential that sustainable development should go ahead with the minimum of delay. That is why we have brought forward this new power. We also think that it is appropriate to have further public and parliamentary scrutiny on how this new power should be used. That is why we have consulted recently on the types of development and why the regulations that follow and prescribe the types of development will be subject to the affirmative procedure.

Other matters were raised. The noble Baroness, Lady Young, who tabled some of the amendments in this group, has had a letter from my honourable friend Nick Boles which I think addresses most of the questions that she raised, but I understand why she would want those responses on the record.