Proceeding contribution from Mark Francois (Conservative) in the House of Commons on Tuesday, 7 May 2024. It occurred during Debate on Defence.

The right hon. Gentleman, a former Armed Forces Minister like me, is absolutely right. Many of them still have half their so-called airframe life remaining. As I have said, they are more than capable of intercepting and shooting down the threat aircraft that they would have to match. That is all the more reason to keep them against a rainy day, rather than flogging them off or breaking them up for parts. Crucially, creating such a war reserve would demonstrate a sign of intent to any potential aggressor that after many years of doing the opposite, the UK is now preparing to fight a sustained conflict with a peer enemy, should that become necessary. Hopefully, in so doing, we will make that eventuality far less likely.

Linked to the vulnerability of our radar stations and the shortage of fighter aircraft are the extremely worrisome delays in airborne early warning. The Royal Navy’s early warning aircraft, Crowsnest, is many years late. It has only recently entered service for the air defence of the fleet. For the Royal Air Force, the Boeing E-3 Sentry AWACS aircraft were withdrawn shortly after the integrated review was published in 2021, leaving us without a mainstream airborne early warning aircraft. The E-3 was meant to be replaced shortly thereafter by the Boeing E-7 Wedgetail, but the programme has been subject to multiple chronic delays and is still not in service.

The RAF is clearly embarrassed by this and is attempting to deploy chaff between in-service dates, when the aircraft could take off the runway, and an initial operating capability, when the aircraft might actually be ready to fight. The latest information I have is that the ISD could now be in autumn 2025, whereas the IOC could be in the first or even the second quarter of 2026, which is still two years away. That leaves a critical gap in our air defence capability for which the MOD, and Boeing in particular, must be held robustly to account. Moreover, the initial buy of five Wedgetail aircraft was inexplicably cut to three several years ago by ministerial fiat, even though we were contractually obliged to buy all five radars, which themselves were very expensive.

In short, the Boeing E-7 Wedgetail is rapidly becoming the RAF’s equivalent of the Army’s Ajax programme—a procurement disaster that has gone on year after year at vast expense to the taxpayer, without actually entering operational service, as Ajax still has not. The Defence Committee, alarmed by that, has invited the head of Boeing Defence, Space and Security, Mr Ted Colbert, to appear before the Committee at Westminster to provide an explanation, although we are still attempting to finalise a precise date for his personal appearance.

Boeing is an organisation in crisis after the sad deaths of more than 300 people caused by the two crashes of its 737 MAX aircraft. We have seen further serious safety incidents, most recently in January when a door flew off an Alaska Boeing 737 MAX 9 in mid-flight. That incident was followed by a number of so-called whistleblowers, involved either at Boeing or in its supply chain, coming forward with very serious allegations about failures in the way the company builds its aircraft. No doubt partly as a result, Mr Dave Calhoun announced that he will step down as chief executive at the end of

the year. In the first quarter of this year, Boeing reported a net loss of more than $350 million, and it is still experiencing serious production problems across a range of aircraft, both civilian and military, of which the UK Wedgetail is but one example. The US Air Force also has numerous issues with Boeing, not least in its much-troubled KC-46 air tanker programme.

For many years, Boeing as a company has done extremely well in winning major multibillion dollar procurement orders from the MOD, in return for which it has placed very limited amounts of work on those programmes with the defence industry in the UK. To give specific examples, according to the MOD’s recent figures, on the E-7 Wedgetail, the estimated UK content is around 10%; for the AH-64 Apache, it is only 7%; for the P-8 Poseidon anti-submarine aircraft, it is barely 4%; and for the original CH-47 Chinook helicopters, it was just 2%. According to the answer to a written parliamentary question I tabled, the UK content for the new order of CH-47 extended-range Chinooks for our special forces will generate a UK workshare of about 8%. Taken together with the purchase of the Boeing RC-135 Rivet Joint electronic reconnaissance aircraft, for which no workshare figure is publicly available, that represents some $10 billion of business for Boeing from the UK MOD for which the UK workshare has been 10% at best and 2% at worst. Boeing has done incredibly well out of the UK MOD, while UK industry has done incredibly badly out of Boeing.