High Speed Rail (London – West Midlands) Bill

I think that engineers are talking to engineers. With the help of the Department, I have certainly facilitated meetings at which the tunnel has been discussed. The problem is that we do not have access to the costings prepared by HS2 Ltd, so we cannot make any comparisons. The truth of the matter is that we can make savings in time and money by reducing the need for those 550 petitions and we can save an area of outstanding natural beauty. If we can protect other areas of the country by kicking up a fuss, we should protect the one that is nearest to our capital city and the one that is so fragile that it would be irreparably damaged if this scheme were to go ahead as currently envisaged.

The office of the right hon. Member for Buckingham (John Bercow) is also concerned that uncertainty still exists for its constituents. During the last petitioning period, it came to light that some people who were affected by the proposal had heard nothing from HS2 Ltd. They heard about their properties being affected only by word of mouth from neighbours. All of us in this House wish to hear that such behaviour will not be repeated in this or any future case.

Following this debate, there will be a consultation on the environmental statement for the additional provisions running from 19 September to 14 November. However, the petitioning period for those who are affected runs only until 17 October. If 56 days have been allocated to look at the environmental impacts, people whose land is affected should not be disadvantaged and expected to respond with a petition in a shorter time frame. Will the Minister consider extending that petitioning period to the same closing date as the consultation on the environmental provisions?

Let me put this matter in context. This project has been going for nearly five years, and because of errors and omissions by HS2 and the Department there have been so many consultations and so many changes to periods of consultations that the closing dates and timetables continue to confuse people. It would be a good idea if we had just one date for the additional provisions. I hope that the Minister will give that thought some consideration.

What assessment has the Minister made of today’s motions and their compliance with key aspects of European environmental legislation, specifically the habitats directive and the environmental impact assessment directive, and the UK’s obligations under the Aarhus convention? As I understand it, the EIA directive requires the entire environmental effects of a project to be measured and consulted on rather than it being done in individual stages through salami slicing. Perhaps the Minister will address that in his response.

I said that I have no intention of dividing the House on this issue as it deals merely with changes to the process for scrutinising the project, but I must again make the point that this project as proposed is deeply unpopular not just with my constituents but with many

others who, like me, do not think that the business case, the route and the lack of connectivity to other transport hubs justify the vast expenditure.