Question
To ask the Secretary of State for Foreign and Commonwealth Affairs pursuant to the Answer of 1 July 2009, Official Report, column 284W, on departmental contracts, what the monetary value is of each contract entered into by his Department during financial year 2008-09 with (a) Alfaplan Gradenje, (b) Asbestos Removals Logistics Ltd., (c) ATG Access Ltd., (d) Bymaro, (e) Controlled Building Services Ltd., (f) Gilbert Ash Fit-Out, (g) Gleeds (QS), (h) Gleeds Building Surveying, (i) GMW Architects, (j) HOK International, (k) Jordan + Bateman, (l) Knight Frank, (m) Mayfair Building Services, (n) Orostream International Contracts Ltd., (o) Ove Arup, (p) Ridge and Partners, (q) Toffco SDN BHD, (r) Windell Ltd. and (s) Zeal Interiors.
Answer
The Foreign and Commonwealth Office (FCO) only has a static database of all of its contracts in the UK and overseas which was compiled in the latter part of 2008. Work is currently being undertaken to convert this to a real time database. To gather all of the contract information for 2008-09 would involve disproportionate cost so the following response reflects records kept by the two contracts teams in the FCO and FCO Services for 2008-09 which will cover a high proportion of the contracts awarded by the FCO in the UK during the period.
Monetary value (£) | Comment | ||
Alfaplan Gradenje | Dubrovnik Consulate Fit-Out works | 53,202.37 | Contract sum |
Asbestos Removals Logistics Ltd | Singapore Asbestos Removal | 76,614.00 | Contract sum |
ATG Access Ltd | Athens Perimeter Security Works | 435,515 | Contract sum |
Bymaro | Rabat—Fire and Flood reinstatement | 1,205,102 | — |
Controlled Building Services Ltd | Addis Ababa Office Extension | 370,479.00 | Contract sum |
Gilbert Ash Fit-Out | Ibiza re-model and Fit-Out (Stage 1) | 25,928 | Contract sum |
Prague Refurbishment of Offices | 498,894 | Contract sum | |
Georgetown Office Modifications | 447,568 | — | |
Gleeds (QS) | (See various contracts for Gleeds listed under Gleeds Building Surveying following) | — | — |
Gleeds Building Surveying | Tehran—Tender analysis | 4,707 | Framework Consultants |
Dubai—Gatehouse OS Commission | 14,547 | Framework Consultants | |
Basra—Office Fit-Out | 63,000 | Framework Consultants | |
New Delhi—Strategic Review of Compound | 210,502 | Framework Consultants | |
GMW Architects | Tripoli—New Offices | 40,250 | Framework Consultants |
Jeddah—architectural services | 14,445 | Framework Consultants | |
Tripoli—Architectural services | 7,759 | Framework Consultants | |
HOK International | Mexico City—Multidisciplinary services | 73,376 | Framework Consultants |
Boston—Architectural Duties | 168,703 | Framework Consultants | |
Jordan + Bateman | Portimao Consular Fit-Out | 254,439.67 | Consultant to Sherman Projectos e Servicos |
Architectural Design Services | 34,560.00 | Framework Consultants | |
Baku—New Residence | 557,506.00 | Framework Consultants | |
Dubai—Gatehouse architectural Commission | 35,094.00 | Framework Consultants | |
Knight Frank | Americas Property Evaluation | 250,000 | Contract sum |
Mayfair Building Services | Caracas Safety and Rewire Works for Residential Properties | 52,399.17 | Contract sum |
Orostream International Contracts Ltd | Kabul Internal Fit-out works | 637,152.39 | Contract sum |
Bogota 8th Floor Fit-Out | 226,336.00 | Contract sum | |
Khartoum Replacement of Chillers | 135,364.00 | Contract sum | |
Minsk Relocation of Classified Area | 287,050.00 | Contract sum | |
Port Stanley Office Extension and Fire Precaution Works | 188,010.35 | Contract sum | |
Podgorica New Embassy and Residence | 778,000.00 | Spend figure | |
Ove Arup | Kuala Lumpur COW services | 18,913 | Framework Consultant |
New Delhi—Strategic Review of Compound | 13,500 | Framework Consultant | |
Canberra—Security works | 84,116 | Framework Consultant | |
Ridge and Partners | Podgorica New Embassy and Residence | 90,000 | Spend figure |
NW Europe Asbestos Surveys | 77,785 | Framework Consultant | |
Tripoli—Asbestos Surveys | 9,032 | Framework Consultant | |
Rabat—PM services | 29,207 | Framework Consultant | |
Belgrade—Feasibility Study | 25,000 | Framework Consultant | |
Ottawa Office—Upgrade | 211,000 | Framework Consultant | |
Khartoum—Asbestos surveys | 11,977 | Framework Consultant | |
Basra—Office fit-out | 14,622 | Framework Consultant | |
Belgrade—Facade Repairs | 22,752 | Framework Consultant | |
New Delhi—Asbestos Review | 9,960 | Framework Consultant | |
Toffco SDN BHD | Kuala Lumpur Repairs to Residential Block and Staff Club | 19,013.04 | Contract sum |
Kuala Lumpur Car Park Waterproofing works | 83,992.80 | Contract sum | |
Kuala Lumpur: Replacement of East Perimeter Wall | 276,434.00 | Contract sum | |
Windell Ltd | Singapore Blast Enhanced Glazing | 570,466.00 | Contract sum |
Zeal Interiors | Wellington—Office Refurbishment | 215,163 | — |